Calculating Man Hours in P6

Beth SpiveyMember for 19 years 9 months
Created
6
1
0
I resource loaded my activities using a 5D/10HR calendar to calculate my manhours by each craft/discipline. I have gone to User Preferences/Calculations and I have the button set to Recalculate the Units/Duration etc. button. I went to Enterprise and resources and have it defaulted to 10H/D. When I change my resources it does NOT recalc my manhours. And if I rollup my discipline/craft to summarize my duration and budgeted units the totals are not accurate if you add them up manually. I have my activity type set as Fixed Duration/Units.

What am I missing?

Thanks in advance. Beth

6 replies

Oldest first
  1. 0
    Beth Spivey ·
    I meant in P5
  2. 0
    Ken Barrett ·
    When you change your resource you might need to manually input the budgeted units / duration / budgeted units/time. When a resource is changed the units somtimes automatically revert to whatever you have as a default setting. Also if you go to the Assignments tab on the tool bar on the left hand side of the screen, it should have a list of all the resources you have in the schedule and their units (you may have to go to the column settings to add the columns that you need).
    I hope this helps you out

    Ken Barrett
  3. 0
    Beth Spivey ·
    Ken,

    Thanks for your response. My only concern is when we made major changes in resources I had to manually recalc and enter the manhours or completely remove and reassign which is very time consuming. And P3 would recalculate itself.

    I am thinking P3 was much better.
  4. 0
    Duy Huynh ·
    Hi Beth,
    Did you try this option: Tools>Recalculate Assignment Costs....

    It will help your problem solved.

    Duy.
  5. 0
    Dieter Wambach ·
    Hi Beth
    Did you have a look into your user preferences?
    Edit --> User Preferences --> Calculations
    For better knowledge, then try "Help"

    Regards
    Dieter
  6. 0
    Beth Spivey ·
    Thank you all for your responses.

    It was the type of duration I had assigned. I changed to fixed units/time and it corrected all my activities.

    Again thanks!

    Beth