IMPORT P3 PROJECT TO P6 IS PAIN....BIG ISSUE

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
3
1
0
HI Dear Friends,
I am facing a big problem of importing the p3 (project planner 3.1) project to p6 6.1 version. The problem is the original budgeted units are getting huge difference in p6.
I tried to import a proj into p6 from p3. In p3 the budgeted unit was 90hrs and but when i imported it into p6 its give 800hours... I been ......f....d in the meeting ...I just thought p6 is reliable and wont make me wrong..............

Pls if you have any clue pls share....
Thx
Suresh

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Suresh
    Just two ideas:
    1. Parameter Planning Units: Hours or Days: May be you selected days but planned in hours.
    2. Resource curves: Sometimes not really compatible - e.g. "curve A" bell shaped in P3, triangle in P6.
    May be others have more ideas.
    Regards
    Dieter
  2. 0
    Suresh Sankarankutty PMP ·
    Diater,
    The units are same in p3 and p6. What i found is.. Unit per time in p3 is getting wrongly calculated in the p6

    Eg: 8hrs per day calender
    unit per day is specified in p3 is 4 duration is 10 days

    In p6 it converts like this

    4*10=40*8 = 800h i dont knnow how its come.. but i think this is the funda... bullshit p6..

    Cheers



  3. 0
    Dieter Wambach ·
    Suresh
    If you walk through the import you see a window "Update Project Options". Select "Advanced" in the bottom of this window. Then try "units as hours".
    Sorry, one of your sentences I don’t understand: "... in p3 is 4 duration is 10 days". What do you mean by this 4 = 10 ???
    Regards
    Dieter