Removing Progress on a Project using P6.2 ?

Mohammed WasiuddinMember for 17 years 7 months
Created
3
5
0
Hai,
could anyone help me on the following concern please,
How can i remove progress on a project with the help of global change while using P6.2(what are the parameters should be)
This can be done in P3 using Then statement
Actual start eq “ “
Actual finish eq “ “
Per.comp% eq 0
RD eq OD

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mohammed,

    It is the same.

    "Actual Start" Equal "Blank"
    "Actual Finish" Equal "Blank"

    Note: Blank means you don’t need to put any value, just leave it blank.

    HTH.

    Regards,

    Arnold
  2. 0
    Mohammed Wasiuddin ·
    Thank you Mr.Arnold .
  3. 0
    Arnold Puy ·

    You are welcome.