Project must finish by

Hatem HussenMember for 18 years 7 months
Created
3
3
0
Some of my projects when i convert them from P3 to P5 and the project finish date for example is 1/4/2009 and the Project must finish by is 1/4/2009 the total float is coming -1 day
can any body help pls

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    P5 works in hours & minutes but you have elected to view the results in days. This means that it has to round -0.5 days of float up to read “-1.” Change your user preferences to view hours and minutes and to see your durations with decimal fractions and you will probably see the cause of your odd reading. Good luck!
  2. 0
    Hatem Hussen ·
    thanks Ronald
  3. 0
    Arnold Puy ·
    Hi Hatem,

    I addition to what Ronald said, check your user prefences -> Dates -> Time, check the box next to 12 hour. Check your project must finish date against with your Activity finish date. try to change the 12:00AM to 5:00PM

    Try to compare these two things, thy must be equal in date and in time.


    Regards,

    Arnold