Planned % data.

Shahzad AhmadMember for 18 years 8 months
Created
1
2
0
Hi,

could any pne help to solve the my problem.

i have a 100 activities for execavation which will be start first week of my project and last execavation will be finish in end of 12 week of schedule.

how i can calculate each week planned % for execavation.

likewise first week 1o% 2nd week 15% 3rd week 20% up to 12 weeks.


I nedd to produce s-curve in xcl format also.

Thanks in advance.

1 reply

Oldest first
  1. 0
    Abdul Khadeer ·
    Hi,

    You can have planned % weekly only in case if you have loaded your activities with quantities or assigned a resource (by weight loading).

    Then you can generate a resource sheet with week on timescale and selecting that resouce.

    if your resource is with cost you will get a curve if you go for profile with cost and cumulative options.

    Try this.

    Cheers
    AK