Planned % data.
In the Open Standard
Shahzad AhmadMember for 18 years 8 months
- Created
- 1
- 2
0
Hi,
could any pne help to solve the my problem.
i have a 100 activities for execavation which will be start first week of my project and last execavation will be finish in end of 12 week of schedule.
how i can calculate each week planned % for execavation.
likewise first week 1o% 2nd week 15% 3rd week 20% up to 12 weeks.
I nedd to produce s-curve in xcl format also.
Thanks in advance.
could any pne help to solve the my problem.
i have a 100 activities for execavation which will be start first week of my project and last execavation will be finish in end of 12 week of schedule.
how i can calculate each week planned % for execavation.
likewise first week 1o% 2nd week 15% 3rd week 20% up to 12 weeks.
I nedd to produce s-curve in xcl format also.
Thanks in advance.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?