Durations in P6

Arvind RamaganapathyMember for 20 years 2 months
Created
1
2
0
I have noticed that while making a program on P6, the Start and Finish Dates are the same but the total durations are different!! I have checked all the settings and they are same. Why is this the case?

1 reply

Oldest first
  1. 0
    A D ·
    summary bar durations are based on global calendar.

    For both the durations to be same, project calendar shud match with global calendar. Thats P6....

    (Drop me a mail at ravirajab@yahoo.co.in regarding your whereabouts; long time no c hmmmmm)

Log in or join to reply