How can one express uncertainty of an estimate using P6 or P5, example 90% probability that a P90, P50 OR P10 estimate schedule will be attain or exceeded

1 reply

Oldest first
  1. 0
    Anu Tor ·
    As your query that one is the risk analysis. My understood, P5 or P6 can not preformed as your want. You need to manual action optimistic, most likely and pessimistic in excel or use pertmaster softwear.