Skip to content

percentage of completion

Anbin PonnithMember for 17 years 4 months
Created
0
2
0
Dear All

1)While scheduling in P3 the percentage of complete shown in the gantt chart is different from the percentage of complete shown in scheduling report.

2) P6 scheduling report does not show the percentage complete? Is there any option for it to show the percentage complete.



Regards,

Anbin Ponnith

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?