Project Progress

Arun VasanthMember for 17 years
Created
2
0
Dear Guys
I have made a Master Program with out resourse loading.
Please help to update the progress.Which progress I have to put for the Progress Updation..

Activity % Completed.
Duration % Completed
Performance completed
Physical % Completed
Units completd

Which I have to use .Please guide ...

2 replies

Oldest first
  1. 0
    A.Jaffer Sadiq ·
    Hi

    You can take Physical Completion %

    Because you’re not done resources load program. If that

    program resources loaded means you can take Activity%

    completion, you will get correct % Completion of your project.

    This only Vertical Project this suitable,

    Ok thanks

    Jaq
  2. 0
    Rodel Marasigan ·
    Arun,
    Activity % Complete = Performance % Complete = to any Percent complete type selected.
    Activity % complete don’t have summary but Performance % complete have.

    If depends how you want to update and monitor your progress. Make sure you maintained and assigned baseline first.
    If you use Physical % Complete every thing needs manual update (i.e. remaining duration, At Completion if different to budget)

    If you use Duration type combined with Fixed Duration and Unit or Fixed Duration and Unit/Time it will synchronized the update of Remaining and At completion.