P6 Export Issue
In the Open Standard
Nithin ThomasMember for 20 years 8 months
- Created
- 2
- 2
0
Dear All,
I resource and cost loaded my schedule of P6 and upon exporting the same file for the review of consultant. He find the same file without any costs assigned to it. Budgeted Units do not vary from the original program, however costs do not get copied.
The other problem I am facing is after loading more than one resource on an item, the budgets cost for all previously loaded resources move directly to 0, be it material or labour.
Do you have any solution to the above problems?
Thanks
Regards
NT
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?