Import Multiproject Plan in P6 from MS Project
In the Open Standard
Jhorbam Baena OrozcoMember for 17 years 1 month
- Created
- 0
- 2
0
Hi everyone.
Well my question is the following...how i can import in P6 a multiproject plan from Microsoft Project?...I explain me, I have in MS Project a Project Plan conformed by 7 individuals projects plan (7 individual files) and linked by external links between them...well i need to import the project in P6, but when i tried that, P6 don't respect the external links and the principal project (the project that call the 7 projects)...this appear empty.
Can someone help me in this dilemma?
Thanks