P6- In a 2 shift manhour distribution not seen.
- Created
- 0
- 1
Dear All,
I prepared the schedule for a shutdown & loaded with resources.Unit of time used is Hrs. & the calender used is 24/7.
I wanted to view the activity distribution over the project time in 2 shifts,I selected the spread sheet on the top screen and the graph at bottom screen.
I selected the timescale>>Date Interval as Day/Shift>>Shift Calender as 2shift shutdown).
Now, I can see distribution of Manhours in Spread sheet in 2 shifts (in p6) BUT I cannot see the same distrubution in graph.In graph, I can only see the bar on only one shift and the other shift is shown blank ( there is no bar on the other shift).
In the picture you can see the bar on 19 (shift) & no bar on 7 (shift)
Waiting for your usual support.Thanks a lot in advance.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?