Cannot Delete the Project Because The Project is In share Mode

Anbin PonnithMember for 17 years 4 months
Created
1
1
0

Hai

One of my Colleague is facing problem with following Issue i

1.Cannot delete the project beacuase the project is in Share Mode

How can we Change the project from Share Mode to Exclusive Mode .

He using P6.7 Oracle Database

2.When he Check the User Dialogue Option from File -> open he got Event code Error -CVRJC-0348-8

3.He forgot the Oracle Password that he typed During Installation of P6.7

Is  there any way to Retrieve the Password

 

Regards

Anbin

1 reply

Oldest first
  1. 0
    Brave G ·

    Try this go to the top of

    Try this go to the top of your screen.

     

    FILE > OPEN> CLICK ON THE PROJECT AND AT THE BOTTOM  SWITCH TO EXCLUSIVE MODE....

Log in or join to reply