Skip to content

Filter of OBS to certain project

Ayman EleishMember for 15 years 9 months
Created
4
1
0

Dear All,

How can I filter the OBS to certain project only?,and can I copy them to word file?

Thanks,

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ayman What is an OBS? Best

    Hi Ayman

    What is an OBS?

    Best regards

    Mike Testro

  2. 0
    Ayman Eleish ·

    Hi Mike, The OBS is the

    Hi Mike,

    The OBS is the organization Breakdown Structure,it is used to identify the employees skeleton of your company,so that you can assign the responsibilities for each one and the relevant WBS.(WBS is the work breakdown Structure).

    You can access the OBS from Enterprise tab in P6.

    Ayman

  3. 0
    Ma As ·

    Dear,   OBS= Organization

    Dear,

     

    OBS= Organization Breakdown Structure

  4. 0
    Rafael Davila ·

    Most companies have multiple

    Most companies have multiple OBS as a person can report to a manager for certain functions while this person at the same times report to other manager for other functions.

    The electrical crew supervisor can report to the project manager for certain functions while at the same time he reports to the electrical division manager.

    If you cannot account for multiple OBS the functionality falls short.

    OBS functionality among other things is useful for orgamizing your scheduled e-mail notices and reporting that will deppend on your multiple WBS and multiple OBS as per your company standards or specific job requirements.

    For example, if according to OBS:

    According to OBS, opened in the Resource Gantt the user can create the following reports on the whole project, individual departments or resources:

    • Cumulative costs of departments, resources and assignments;

    • Working duration for departments and comprising resources;

    • Work volumes and resource-hours;

    • Individual resources work costs; cumulative costs or resources, comprising departments – in the context of cost components and cost centers;

    • Material consumption by resources and departments;

    • Consumption of materials, organized in material centers;

    • Resource hours of resources assigned to activities execution in resource-hours

    • Cumulative costs of departments, resources and assignments;Working duration for departments and comprising resources;

    • Work volumes and resource-hours;

    • Individual resources work costs; cumulative costs or resources, comprising departments – in the context of cost components and cost centers;

    • Material consumption by resources and departments;

    • Consumption of materials, organized in material centers;

    • Resource hours of resources assigned to activities execution in resource-hours 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?