Skip to content

P6 Early finish date is stucking in the project data date

Emre OdabasMember for 14 years 9 months
Created
2
2
0

I am not able to change the early finis date for a finished activity even if the completion date is seen correct in activity details tab and in actual finish date. I am changing the date but whenever scheduling the project data date comes back. I tried to change all the variables (activity types, constraints, removed relations etc.) but I couldn't succeed. The following image is summarizing my problem:

http://img59.imageshack.us/img59/6118/p6problem.jpg

I am a rookie for primavera and if anyone has any idea about it I will be glad

Thank you

2 replies

Oldest first
  1. 0
    Sethupathy Subramaniam ·

    Dear,After assigning an

    Dear,

    After assigning an actual date for an activity you cannot change the early dates for that activity. 

    P6 assigns the data date for the early start/early finish of any acitvity and also assigns late start/late finish based on the no of days that activity could have been delayed or advanced based on the current update. 

    Simply put - dont try to change the early or late dates of any activity after assigning actuals to the activity. 

     

    Regards

     

    Sethupathy

     

     

  2. 0
    Shareef Abdul Azeez ·

    Hi emre Use Start & Finish

    Hi emre

     

    Use Start & Finish Date fields instead of Early Start & Early Finish.

    Early & Late Dates are dynamic

    Normally activities to left of the Data Date are updated but in ur case ur DD is behind the actual finish date.

    Download the document---Understanding P6 Dates from the website below to get a better understanding on the date fields in P6

    http://ronwinterconsulting.com/published.htm

     

     

    Regards

    Shareef

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?