Hi to All P6 users,
I found discrepancies in Budgeted Total Cost on activity column VS the Cumulative Budgeted Total Cost at the end of the project on the activity usage spreadsheet. Please be reminded to review your schedule & reports.
In the image above the Budgeted Total Cost is 502,798,675 but at the end of the Schedule on the 36th month, the Cumulative Budgeted Total Cost is 502,798,520.
Anyone had encounter the same problem?
What was your solution to it?
Regards,
7 replies