How do I export my project from P6 to MSP??

Praneet KMember for 14 years
Created
2
2
0

I did try exporting the file from P6 and savin it in.mpp format and then open it MSP, but then not all the linkages, dates match exactly?

Can anybody help me on this??

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Praneet,Primavera and MS

    Praneet,

    Primavera and MS Project do not compute the project's schedule exactly the same way; specifically, P6 allows 2 links between the same 2 activities, understands start and finish milestones, and more scheduling constraints than MS Project; it is therefore understandable that the projects do not match from one software to the other

    Alexandre

  2. 0
    Paul Harris ·

    Therea techinical article on

     

    Therea techinical article on mt website covering all the issues with converting from MSP to P6.

    It makes interesting reading!

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
    www.eastwoodharris.com
    www.primavera.com.au - a Primavera scheduling software resources site