EXPERTS call. Baselines quibble.

Marcel FrancesMember for 14 years 3 months
Created
2
2
0

Hi there

This is about baselines.

If I don't assign any baseline and I use the current project as such, I have noticed that for the already finished and already started activities the program keeps the original baseline dates one day assigned to those.

What I am doing is I create a copy of a project, I move de DD in the original project, and finally I assigned that copy created as a baseline in the new DD project. I aim to see the finish dates for the ongoing activities as there were beforer moving the DD.

Any suggestions on what I should do?

Thanks,

Frances.

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Frances,   Go to Admin >

    Frances,

     

    Go to Admin > Admin preferences > Earned Value and change "Earned Value Calculation" setting to "Budgeted values with current dates"

     

    For more info on this common issue, see Paul Harris' excellent briefing here:

    http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

     

    Cheers,

     

    G

  2. 0
    Marcel Frances ·

    Brilliant. Thanks Gary!!!

    Brilliant. Thanks Gary!!!

Log in or join to reply