EXPERTS call. Baselines quibble.
In the Open Standard
Marcel FrancesMember for 14 years 3 months
- Created
- 2
- 2
0
Hi there
This is about baselines.
If I don't assign any baseline and I use the current project as such, I have noticed that for the already finished and already started activities the program keeps the original baseline dates one day assigned to those.
What I am doing is I create a copy of a project, I move de DD in the original project, and finally I assigned that copy created as a baseline in the new DD project. I aim to see the finish dates for the ongoing activities as there were beforer moving the DD.
Any suggestions on what I should do?
Thanks,
Frances.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?