Hello Planners,

Me again...

Is there a way to filter for specific project expense allocations in the 'project expenses' view?
The filter icon is greyed out.
Is this something can be fixed in admin preferences? or am I pushing the limits of P6?

It seems like it would make a lot of sense to be able to filter based on any of the 'project expense allocations' fields.

I guess there is a workaround by doing it through reports though...

Cheers,
Hugh.
 

1 reply

Oldest first
  1. 0
    Manochehr Hosseini ·

    Dear McleayIt seems filtering

    Dear Mcleay

    It seems filtering of the expences is not available in P6, as far as I know there is no settings for that in admin prefrences and even if you login with admin user still you the filter icon is grey.

    Regards,

    Manochehr 