Event Error UPFE(-2175-2

Paul ZachariaMember for 12 years 3 months
Created
3
1
0

While attempting to set up the page or preview the print, i am getting the event error UPFE(-2175-2. If i print the file directly, then, it prints only the first page and shows printing on progress. And there after no result. 

 

Can anyone provide a solution for this error. 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    let me quess you have

    let me quess you have instered a picture or logo into your header or footer with a .shs extension?

    there are 2 possibel solutions

     

    Option #1

    Switch to a Layout that does not contain the '.shs' file in the Header or Footer

     

    Option #2

    Configure Windows so that it displays all File Extensions, including '.shs'.

     To do this Go to the Control Panel and select Folder Options.

    Click on the File Types tab.

    Select the file type 'Scrap Object' with extension 'SHS'.

    Click on the Advanced button.

    Place a check in the box for 'Always Show Extension'.

    Edit the Registry, HKEY_CLASSES_ROOT\ShellScrap.

    Delete the value 'NeverShowExt'.

    Delete any '.shs' files or Rename their extension.  

  2. 0
    Paul Zacharia ·

    Thank you for the reply. The

    Thank you for the reply. 

    The problem was due to the .gif image which was oversized in the header option. I resized the image and saved it as .jpg format and now it is working fine.

     

     

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 