Implementation issues

Scott SetzerMember for 15 years 5 months
Created
1
2
0

 

The IT group has Implementation issues with a new install of P6 R8.3.2. When we are connected to the server data base there is on admin toolbar in the program and a few other fetures are not present. we also get an error about the  industry type has not been selected but without the admin tool bar there is no way to select one. I can run the program as a stand alone and all feature are there.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    all of the admin functions

    all of the admin functions that you are usied to in version 6.2 or 7.2 have been moved to a web browser interface that opens the Primavera p6 resource manager the access to this should be via your server 