how to create a project for piping in p6

Manikanta LokamMember for 10 years 8 months
Created
4
2
0

Hai to all,

           please help me anybody, how to create a piping project having scope (200000 IM and 19000 ID) IN PRIMAVERA P6.

 

MANI

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    define scopecreate wbs

    define scope

    create wbs structure

    create activites

    assign logic

    assign duration

    assign activiites to wbs

    create a resource

    assign resoure to activities

    assign units (manhours) and costs $(dollars) to each resource for each activity 

    f9 calculate schedule

    done

  2. 0
    Manikanta Lokam ·

    hai zoltan,            Thanks

    hai zoltan,

                Thanks for your sugission. presently iam working on ag piping but i am not using p6,we are using only excel.

    i want to use p6 for planning but i am confusing to define wbs and activities. in my project we have scope

    of 354000 IM,34000 ID,600 ISO drawings,24 no.of service pipelines with different sizes and 1 rack(having 126 no.of civil grids with 3 tairs of elevation).please help me to define wbs and activities.

     

    mani...

  3. 0
    Manikanta Lokam ·

    -------------

    -------------

  4. 0
    Zoltan Palffy ·

    very hard to do without

    very hard to do without knowing the scope

    install pipe rack structure level 1

    install pipe rack structure level 2

    install pipe rack structure level 3

    Lay large bore piping rack level 3

    Lay Small bore piping in rack level 3

    Weld or Connect large bore pipe in rack level 3

    Test large bore pipe in rack level 3

    Insulate large bore pipe in rack level 3

    Weld or Connect small bore pipe in rack level 3

    Test small bore pipe in rack level 3

    Insulate small bore pipe in rack level 3

    Lay large bore piping rack level 2

    Lay Small bore piping in rack level 2

    Weld or Connect large bore pipe in rack level 2

    Test large bore pipe in rack level 2

    Insulate large bore pipe in rack level 2

    Weld or Connect small bore pipe in rack level 2

    Test small bore pipe in rack level 2

    Insulate small bore pipe in rack level 2

    Lay large bore piping rack level 1

    Lay Small bore piping in rack level 1

    Weld or Connect large bore pipe in rack level 1

    Test large bore pipe in rack level 1

    Insulate large bore pipe in rack level 1

    Weld or Connect small bore pipe in rack level 1

    Test small bore pipe in rack level 1

    Insulate small bore pipe in rack level 1

    Commissioning of Piping Systems

     

     