Check list for Testing P6

Nafees GhouriMember for 14 years 6 months
Created
3
2
0

I am testing Primavera P6 as a user. My company is migrating our existing server to loadspring to see the impact of change. Is anyone has the checklist, so i coud test these areas so nothing is missed out. Thanks

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    test the performance times,

    test the performance times, import and export functions.

    Make sure that you do not bring any POBS tables over to the new database

  2. 0
    Nafees Ghouri ·

    Thanks Zoltan,Just to know

    Thanks Zoltan,

    Just to know what are POBS tables.

  3. 0
    Zoltan Palffy ·

    POBS tables stand for Project

    POBS tables stand for Project Organization Breakdown Structure. they are not used and they can really slow down a database

    here is a link to what POBS tables are as well as a free cleaner for xer files 

    http://scheduleanalyzer.com/sae_p_POBS.htm