Hi Everybody!
Is it possible to show a custom line on Gantt Diagram showing the difference between Finish Date and BL Finish Date?
In Line Filter I only can compare one of them to specific numeric value and I need to compare them against each other and paint the difference in red color.
For Example my current situation
And what I want to show
I only able to draw all line in red, but I want only part of it being red.
Will be glad to hear any suggestion how to do it.