How Do You Manage and Validate LOE Activities in Primavera P6 on Real EPC Projects?
- Created
- 0
- 2
Hello everyone,
I have been working in Planning and Project Controls for over 20 years, primarily on major Oil & Gas and Offshore EPC projects.
I would like to hear how other experienced planners handle Level of Effort (LOE) activities in Primavera P6, particularly when dealing with complex schedules, multiple calendars, and progress measurement.
I am especially interested in the following practical questions:
1. LOE Relationships and Duration
Do you normally use SS and FF relationships to tie LOE activities to the underlying discrete activities or milestones?
Have you encountered situations where LOE start or finish dates, or their duration, behaved unexpectedly after rescheduling?
How do you handle LOE activities spanning multiple calendars?
2. LOE Progress Measurement
Do you typically measure LOE progress using elapsed duration, actual versus planned duration, or another method?
How do you handle LOE progress when the underlying activities are delayed or extended?
Do you use different measurement rules for engineering management, supervision, project controls, or other indirect activities?
3. LOE and Earned Value Management
Do you assign budgeted manhours or costs directly to LOE activities?
How do you calculate or validate earned value for LOE activities?
How do you avoid overstating project progress when LOE activities earn value primarily through the passage of time?
4. Schedule Quality and Validation
What checks do you normally perform to ensure LOE activities are not distorting critical path analysis, float values, or schedule performance indicators?
Are there any recurring LOE issues you have encountered when reviewing schedules submitted by EPC contractors?
I would also be interested in hearing whether your approach differs between the EPC contractor and client/operator sides.
I am particularly interested in actual industry practices rather than purely theoretical scheduling rules, as I have seen different approaches across projects and organisations.
Any practical insights or lessons learned would be greatly appreciated. No confidential project information is needed.
Thank you in advance for sharing your experience.
Best regards,
Zhenya
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
Related across the Open Standard
Knowledge
- Critical Path
WikiShares "Critical path" · Shares "Schedule development"
- Critical Path DRAG
WikiShares "Critical path" · Shares "Schedule development"
- Logic, Leads & Lags
WikiShares "Logic" · Shares "Schedule development"
- Critical Path Method
WikiShares "Critical path" · Shares "Schedule development"
- Finish to Start Vs Start to Finish Relations in Primavera Project Planner P6
WikiShares "Logic" · Shares "Schedule development"
Discussions
- How many types of activity floats exist in the context of project delivery date(s)?
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- S curve model of adoption rate, Excel
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- Web Based Time Tracking Software
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- No Subject Specified
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
- Dredging Productivity
0 repliesShares "Critical path" · Shares "Logic" · Shares "Schedule development"
Blogs
- Baseline Change Management
Shares "Critical path" · Shares "Schedule development" · Shares "Primavera P6"
- Failing Fast-For the Rest of Us
Shares "Logic" · Shares "Schedule development"
- Time Equals Money
Shares "Critical path" · Shares "Schedule development"
- Programme Planning Standards: The Rules of the Game
Shares "Critical path" · Shares "Schedule development"
- Confidentiality of Project Data When Shared in XER File Format
Shares "Schedule development" · Shares "Primavera P6"
Jobs
- Planning Claims Analyst
Shares "Schedule development"
- PMO Analyst
Planning Planet · LondonShares "Schedule development"
Norms
- Pharmaceutical
Rates, Norms & DurationsShares "Schedule development"
- Elevated Watercourse
Water ManagementShares "Schedule development"
- Health & Healthcare
Rates, Norms & DurationsShares "Schedule development"
- Automotive
Rates, Norms & DurationsShares "Schedule development"
- Rule of Thumb
Rates, Norms & DurationsShares "Schedule development"