Hey, my first thread! Here goes hope you can help.

The company I work for uses MS Project 2002. We use the Progress Mail functionality via e-mail and update the plans with assignees work daily via this method.

Recently, due to a crash on the Resource Pool 11 of my 27 plans took a trip to the funny farm and were returned via back-up from the day previous.

My issue is now that when the progress mails are updated, all previous days time for the given task/assignment are given a zero from the start of the task and only the day the mail is updated registers any time. Does this make sense. Not sure if I am explaining it well. Basically I think the issue is with the Effort Driven aspect/checkbox within the task properties as all tasks seem to have defaulted to checked. So I am currently opening the progress mails and updating the plans manually, this works fine...for now.:-(

On changing this to unchecked the tasks revert straight back to checked on reopening the project after saving.

Any and all assistance is greatly appreciated.
Many thanks, I feel this may be something and nothing.

Regards

4 replies

Oldest first
  1. 0
    Bernard Ertl ·
    Hi Kevin, welcome to the Planning Planet!

    You should have posted this in the Microsoft forum for better visibility of members who use Microsoft Project since this a software specific issue.

    Bernard Ertl
    InterPlan Systems - eTaskMaker Project Planning Software
  2. 0
    Forum Guest ·
    Unfortunately I did and they have taken some 4 weeks to even return mail. I sent a copy of one of the plans for reference but to no avail. They refered me to message boards and forums...

    I was really hoping that someone may have come across this problem before.

    Many thanks for the welcome. :-D
  3. 0
    Bernard Ertl ·
    Kevin, I meant the Microsoft forum (category) here at the Planning Planet. This is the general planning & scheduling category.

    Bernard Ertl
    InterPlan Systems - eTaskMaker Project Planning Software
  4. 0
    Forum Guest ·
    Ahhh...

    Will do.


    {:-|}