P3 - Project Environment Variable - too long

George KaramMember for 22 years 3 months
Created
2
2
0
when opening a schedue from a copy / backup this message appears. "Project Environment Viariable - Too Long" As a result, the schedule cannot be time analysed, the reports do not work. Has anybody experienced this problem? please advise

2 replies

Oldest first
  1. 0
    Berli Berli ·
    Dear George,
    Please try to move your P3 files directory to upper level directory such as C: or in your P3winProject folder.

    Regards,
    Berli
  2. 0
    Ronald Winter ·
    The complete name of your drive:directory cannot be longer than 64 characters. Next time, please post your inquiry in the proper forum (ie. P3). This discussion is closed.

Log in or join to reply