Skip to content

calculate project weight by cost

Kamyar SanandajiMember for 22 years
Created
4
2
0
as a factor for weight value of an EPC project In GAS PIPELINE field i want to distribute the weight to my main WBS items in this case i saw lots of discussions that happend in the forum, but nobody didnt mentioned about any refrence that can show how to calculate it for such EPC project, is there any standard or refrence that can modified for these type of projects?

4 replies

Oldest first
  1. 0
    Luca Basile ·
    Kamyar,
    it is a lot in function of the company for which you are working.
    I saw different company allocating the weight different.
    It depennd in which area the fell stronger.

  2. 0
    Randa Shammas ·
    Kamyar,

    I work for an EPC company as well and this is how weight is usually distributed on the three phases (Engineering, Procurement, and Construction).

    For Engineering, % wtg is distributed according to the ENGINEERING MANHOURS needed to produce different engineering documents. This is usually given to you by the different engineering disciplines, and it is your job as a planner to allocate these manhours and distribute them along the engineering phase of your schedule.

    For Procurement , weightage is relatively easier to calcuate here since it is based on COST. Basically the more expensive materials / equipment will have a greater % wtg then the less expensive ones.

    For construction, weightage is based on QUANTITIES.
    Mechanical equipments will be in Tons
    Structural Steel will be in Tons of Steel
    Concrete pouring will be in m3 concrete.
    Electrical and instrument cables will be in Lm
    Excavation will be in m3
    etc....

    there are many many quantities. These quantities should than be transformed into CONSTRUCTION MANHOURS which is done by multiplying by production rates. example: hrs/m3, hrs/ton of steel, etc... These production rate are available here on the plannig planet site. just go to the Prod-rates section. After you’ve got your construction mnhrs ready you have to convert that to % wtg. Roughly the activities with the larger construction mnhrs (aka larger quantities) will have the larger weight factors.

    Commissioning I believe is done like construction, but you should check on that cause i’m not sure.

    I hope this helped.

    Good luck,

    Randa
  3. 0
    Dylan Wan, PMP EVP ·
    Do you weight your WBS items by their duration? Can you share when you will use "duration" as the weight basis?
  4. 0
    Kamyar Sanandaji ·
    No i dont use duration for weight % because it will cause some problem,example: in some activity such as maintenance activities that they have long duration & low weight value Vs. construction works.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?