Schedule Variance Procedures

Dana FitkowskiMember for 20 years 2 months
Created
2
4
0
Hello!

I was wondering if anyone was able to help, our group is looking for any info on writing a procedure for schedule variance reporting. Any examples or samples would be much appreciated.

2 replies

Oldest first
  1. 0
    Peter Holroyd ·
    key data to be derived from the schedule is

    1 SPI performance on an accum and period basis of current v baseline programmes - this gives the history then look forward by
    2 SPI Index to Completion - this is the improvement required to finish the job on time (assuming you are behind)from which you can see whether it is realistic
    3 Print out the top (5 ?) critical paths on the project and make sure they are sensible and everyone knows which are the current activitites on these critical paths
    4 then as a test to see if you programme is getting more critical try a Float Trend Analysis graph
    5 a simple Principle line would be nice but most software doesn’t support this

    Hope this helps
  2. 0
    Dana Fitkowski ·
    Thanks very much Peter, certainly does help us out.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?