Project Duration
In the Open Standard
Weni SamsonMember for 19 years 11 months
- Created
- 7
- 4
0
I need help from you guys. Sorry but am just a neophyte in this field. Actually,I am preparing a time schedule for a 3Basement+56Floors building with the following details:
1. Basement to 6th Floor Dimension --> 80m x 40m
2. Structural Height ---> 3.20m
3. Parking Floors ----> Basement 3 to 6th Floor
size 80m x 40m
4. Office Floors ----> 7th Floor to 21st Floor
size 60m x 30m
5. Residential Floors ----> 22nd Floor to 52nd Floor
size 60m x 30m
6. Health Club Floors -----> 53rd Floor to 54th Floor
size 60m x 30m
7. Mechanical Floors -----> 55th FLoor to 56th Floor
size 60m x 30m
8. External Facade ------> 20% Aluminum Cladding
10% Plaster Painted Finish
70% Curtain Wall Glazing
I need to know the complete project duration with some duration on how many weeks the sub-structure, super-structure, excavations, piling, curtain wall, cladding, finishes, etc. as wellas the proper activity sequencing or linking.
I appreciate most whatever help you may impart on this regard.
Thanks a lot in advance.
1. Basement to 6th Floor Dimension --> 80m x 40m
2. Structural Height ---> 3.20m
3. Parking Floors ----> Basement 3 to 6th Floor
size 80m x 40m
4. Office Floors ----> 7th Floor to 21st Floor
size 60m x 30m
5. Residential Floors ----> 22nd Floor to 52nd Floor
size 60m x 30m
6. Health Club Floors -----> 53rd Floor to 54th Floor
size 60m x 30m
7. Mechanical Floors -----> 55th FLoor to 56th Floor
size 60m x 30m
8. External Facade ------> 20% Aluminum Cladding
10% Plaster Painted Finish
70% Curtain Wall Glazing
I need to know the complete project duration with some duration on how many weeks the sub-structure, super-structure, excavations, piling, curtain wall, cladding, finishes, etc. as wellas the proper activity sequencing or linking.
I appreciate most whatever help you may impart on this regard.
Thanks a lot in advance.
7 replies
Oldest firstLog in or join to reply