Global WBS or Project Specific WBS

Richard DayMember for 18 years 3 months
Created
1
2
0
In Primavera 6.1 is it better to use a Global WBS or a Project Specific WBS?

I am scheduling about 100 projects with monthly updates.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Depends on your needs for reporting.
    Internal projects, stakeholders need reports on all projects: Global wbs to e.g. level 2 or 3, more in detail, upon pm’s decision.
    Independent projects with different stakeholders: Easier for you with a standard wbs (templates!). May depend on the projects’ stakeholders.