Skip to content

Small Project

Azeem AbdulMember for 17 years 11 months
Created
3
3
0
Hi Planners

Can any one Plz forward me the sequence of a Small Building Project for an area of 2400 Sq Ft.(60’x40’)From foundation to G+3 including 20 RCC Columns in it.

Thanks U

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Azeem,

    The activities are:

    1. Excavation
    2. Blinding
    3. Shuttering for Foundation
    4. Reinforcement for Foundation
    5. Concreting foundation
    6. Reinforcement Vertical Elements (20 columns)
    7. Shuttering vertical Elements
    8. Concreting vertical Element
    8.1 Insulation vertical Elements
    9. Fill and compaction up to SOG
    10. Blinding for SOG
    11. Insulation for Slab on Grade
    12. Reinforcement for Slab on Grade
    13. Concreting of Slab on Grade
    Repeat for each level: G+ L1, L2, L3
    14. Reinforcement vertical Elements
    15. Shuttering vertical elements
    16. Concreting vertical elements
    17. Deshuttering vertical elements
    18. Shuttering for Slab
    19. Reinforcement for Slab
    20. Concreting slab.

    These are the basic activities, you will need to fill in the blanks as per the Contract requirements.

    Let us know if you need more assistance.

    Best,

    Samer
  2. 0
    Ahmed Khan ·
    Thank U very much samer,

    Could U Plz forward me in detailed with the durations of activities.?

    Regards

    Maask
  3. 0
    Samer Zawaydeh ·
    Dear Maask,

    Before you determine the duration, you need to assign the resources; manpower, material and equipment. Depending on the productivity rates, you will determine the duration.

    You will need to talk to your team members for determining the available resources.

    Best,

    SAmer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?