Dear All,
greetings,
I builded aprogram by p6 but,i not load both resources and cost and updated this program my question ,how to find the precentage for overall project.




thanks
amro

4 replies

Oldest first
  1. 0
    Sampath Lakshmi Narayanan ·
    No problem..You Update the schedule with the latest data date and run the schedule. You will be getting the latest Duration percentage progress ....
  2. 0
    Amro Ahmed ·
    i know that but the precentage based on duration usulaly not very accurate i want to get precentage based on real progress from overall activities
  3. 0
    James Shimmon ·
    In order to get a BCWS for the project to date you need to allocate costs and resources to the activities
  4. 0
    Sampath Lakshmi Narayanan ·
    Still U can do one thing. U start entering Physical progress percentage in Duration % zone and re check ur remaining duration and expected completion date. This can your problem as physical percentage in Primavera does not have much impact on schedule. Even better way is assign weightages to your WBS and activities in excel, distribute in using start and finish dates and calculate the percentage progress (By Making S Curve)