Change in scope of works and schedule
In the Open Standard
Ismail KhanMember for 17 years 11 months
- Created
- 5
- 2
0
Hello Master Planners,
I just wanna know what is the standard practice if for example i have a MSP detailed schedule loaded with wt. % on each activites and all my planned and earned percentage are generated from my updated schedule and then suddenly a change of scope of works say there is a activity called top over hauling of engines is changed to complete overhauling of the engines and the variation order has been issued to the contractor with a time extension of 2 months.Now what will be the impact in the baseline schedule and the updated schedule.Is it advisible to change the baseline schedule.
Before issuing the variation order the planned progress was 92% and the actual progress is 45%.
Please advice.
Thanks all....
I just wanna know what is the standard practice if for example i have a MSP detailed schedule loaded with wt. % on each activites and all my planned and earned percentage are generated from my updated schedule and then suddenly a change of scope of works say there is a activity called top over hauling of engines is changed to complete overhauling of the engines and the variation order has been issued to the contractor with a time extension of 2 months.Now what will be the impact in the baseline schedule and the updated schedule.Is it advisible to change the baseline schedule.
Before issuing the variation order the planned progress was 92% and the actual progress is 45%.
Please advice.
Thanks all....
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?