Ethanol project period

Anu TorMember for 19 years 7 months
Created
5
3
0
Dear all members,

Could you instruct me the project period of Ethanol plant?
- Engineering = months
- Procurement = months
- Construction = months
The plant capacity is 100,000 million liters / year.

Thank you,

5 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi

    Further more information regarding your long lead procurement is required.Plant projects generally driven mostly by long lead items ,it may not be 100% at least to some extent it is applicable
  2. 0
    Samer Zawaydeh ·
    Dear Anu,

    Very rough estimation, you can start with

    Engineering: 12 months
    Procurement: 12 months
    Construction: 24 months
    Commissioning: 6 months

    Depending on the stage that you are at, you can float few inqueries for Engineering firms, suppliers and few Contractors with similar experiences in your area, and get more feedback.

    With kind regards,

    Samer
  3. 0
    Jay S ·
    Engineering 12 Months
    Longest Lead I think is approx 12 Months (Vessel)Depended on Market
    Construction - 6 to 9 Months
    Commissioning 3 Months
    This can overall as well to a certain Percentage I would say Overall approx 18 to 24 Months
    The Biggest problem Process depends how far the design is or your inhouse capacity/Knowledge.
  4. 0
    Trevor Rabey ·
    This top-down stuff is just pure guesswork, with a bit of experience thrown in, maybe. It doesn’t even rate as an estimate.

    Could just as well be:

    Engineering: 13 months
    Procurement: 11 months
    Construction: 23 months
    Commissioning: 7 months

    Plan the actual project in detail from the bottom up and then you know.
  5. 0
    Samer Zawaydeh ·
    Dear Trevor,

    On average, the initial estimation would be withing 25% error. You are correct.

    The best people to estimate the duration of the project, would be the Design team in association with skilled contractors who have done similar jobs in the past.

    With kind regards,

    Samer

Log in or join to reply