Skip to content

Difference between Piping and pipeline, what is Pipeline project and what is cross country pipeline project.

Shazia khanMember for 18 years 5 months
Created
3
3
0

Hi All

 

I would like konw , basic about pipeline project,

 

what is cross country Pipeline Project, and pipeline project.

 

Best Regards

 

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    Difference between Piping and pipeline, what is Pipeline project

    Shaza Khan,

    I do not see any difference at all, they are all pipes to me.

    As a planner, what you need to know is basically the diameter of the pipe, the lenght of the pipeline and your welding production rates. You also need to know whether it is above ground or underground. If it is underground you need to know the soil conditions, where the pipe is being laid. If it is above ground you need to construct pipe sleepers to protect the pipe. You need to look at the scope of work. Does it require cathodic protection? Does it require insulaton or painting?

    If the pipeline is for Gas or Oil you may need to know about cold cutting and tie-in procedures.

    Best regards,

    Daniel

  2. 0
    Alex Iskandar ·

    Piping and Pipeline Terminology

    hi Shazia, Just for share the knowledge, as I just arrived to this forum ...

    Yes Daniel is right, they all pipes, but to increase our knowledge and just want to share what I've learn from the course

    (If you are an engineer don't hesitate to ask your manager for getting more training in Engineering, to have training such as Piping and pipeline design etc, would increase your skills for planning)

    Piping Terminology;

    1. Transmition pipelines: Usually long, relatively large diameter lines, May Tranport Hydrocarbon fluids and or Gas. from prudocing fields to processing plant or refineries.. From plants and refiniries to marketing centers
    2. Flowline: Two phase lines (Non separted HC with two phase (liquid and gas) flows before entering the inlet separator), connecting welss to production manifolds. range from 2 - 20 inches.
    3. Trunkline: Two or more well flowlines connected to a larger line that carries the combined well stream to the production manifold. range from 10 to 42 inches.
    4. Injection lines: Transport high pressure gas or water to wellheads for injection into the producing formation. Fluids are injected for: Reservoir pressure performance, production enhancements, conservation of gas, Gas Lift, Produced water disposal , waterflood, steam flood.
    5. Piping / Plant (Facility) Piping (on plot) : Piping witihin the well defined boundaries of the processing plants, piping compression station or pumping station. Used for a variety of fluids within those boundaries as required.

    Warmest regards from Indonesia

    Alex Iskandar, PMP

  3. 0
    Shazia khan ·

    Alex,   Thanks for your

    Alex,

     

    Thanks for your explanation this is rely what i was looking for,

     

    construction Sequence. (please correct me if i am wrong)

    Piping- Fabrication

    Pipe sand Blasting painting                                           

    Marking and Bevel cutting.

    Welding

    NDT

    Hydrotes (spool testing.)

    Installation if Ground piping if,

    Erection.

    Erection on the Pipe rack

    Welding erected spool pipe

    NDT

    Hydro test

    Chemical cleaning / passivation.

    Insulation

    or final coat paint.

    Pipeline:

    Stringing of the pipe (on trench Side)

    Welding

    NDT

    wrapping Coating or insulation of pipe Joint

    Lower the pipe in the trench

    Back filling of Trenched

    Pig Cleaning

    Ready for operation.

    Please advise me if this correct sequencing.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?