Project Cost
- Created
- 3
- 3
Hi,
I am trying to create a cost centre for my company here. I have a few question
a) i look at my company bill of quantities and it look scattered and i feel very hard to transfer the cost from my excel sheet prepared by my estimator to the programme. An example of the excel sheet as below. this is only 1 page and this project has 100 pages of excel sheets. sometime, the items in the programme are not the same and sometime, for example, the excavation item done by my estimator include the concrete cost as well. i am afraid i will make a mistake for sure in the end of the thing and i feel very difficult to input the bill of quantity cost to programme. anyone has the same problem? i feel its even impossible to ask my estimator to input all the cost to programme when they do the tendering work? is this an idea or it happen in reality? if yes, how can i do this please?
b) i look at the cost that i think i should divide to manpower, material, plant and subcontractor. should i put more? or just put a total cost which make my life easier? any planner to advise please?
c. the programme cost below show when the cost incur but not show the when exactly the my company pay. for example,
i. company pay the subcontractors on the 14th and 30th every month
ii. company pay the supplier on the 14th every month
iii. company pay the plant on the 14th every month
iiii. company pay the labour/manpower on the every wednesday which start count from friday 8 working day.
to be a planner, do i need to show the real cost or just put the incur cost happen on every task?
c. i feel confuse how should i use the programme to control the company cost, this is my question eventually, thanks.
Regards,
Mike
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?