Exporting Open Plan Professional to MS Project

Reggie WinfreyMember for 14 years 9 months
Created
1
2
0

Is there a way to export an open plan professional schedule, which is resource loaded, to ms project to include the resources as well?  I have imported it once, but not all of the resources came across properly and the resources that did come across were inflated.  I'm open to any suggestions.

1 reply

Oldest first
  1. 0
    Matt Woj ·

    Reggie, You will probably

    Reggie,

    You will probably have to do a crosstable export for the resources and then import them into MSP.  The regular MSP export does not work well to getting both out.