Project tracking problem
In the Open Standard
Ravirg GehlotMember for 15 years
- Created
- 0
- 4
0
Hello everyone
I am using a schedule of 5000 activities ...there are lot of packages in the schedule & the activity duration is also vey less like 2 hours , 6 hours , and as a whole package the duration become 300 hours ...but i want to show all 5000 activities in schedule, Now the probelm is How to track the activities of small duration ...I mean 2hours , 4 hours etc...Its difficult to Track my schedule ...Any Sugessitions...