Progress on WBS and Project Level
In the Open Standard
Planner BimMember for 14 years 8 months
- Created
- 2
- 2
0
Dear Seniors,
I am new in Planning. Can you please guide me.
What is the best way to measure progress at WBS level and Job level on a project having 500+ activities and 26 WBS, without cost/ resource loading. I selected the option "Performace % Complete" also. After inputting the % Completion in Activity % Completion, I am not getting the % at WBS and Project level.
Please guide me on this.
Thanks,
BIM
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?