Progress on WBS and Project Level

Planner BimMember for 14 years 8 months
Created
2
2
0

Dear Seniors,

 

I am new in Planning. Can you please guide me.

What is the best way to measure progress at WBS level and Job level on a project having 500+ activities and 26 WBS, without cost/ resource loading. I selected the option "Performace % Complete" also. After inputting the % Completion in Activity % Completion, I am not getting the % at WBS and Project level.

Please guide me on this.

 

Thanks,

BIM

2 replies

Oldest first
  1. 0
    Vijay Anbumani ·

    Hi Bim,        I am not much

    Hi Bim,

            I am not much more experienced but i feel i can help you on this, no problem cost or resource not needed but are u using the planning tool of Primavera 6 or MS project. the % Completion u selected is rite but you have to update the schedule. check the progress update and select the regarding month to be update, so u will get it.

    where are you working Bim.

    Yur, & best wishes.

    J. Vijay

  2. 0
    Hlamalani Baloyi ·

    I suggest you dont use

    I suggest you dont use Perfomance % if your schedule is not cost loaded.