Project scheduling with limited data
- Created
- 4
- 2
Dear All
I need your advice rgarding following issue;
I have been given a task to plan an oil refinery project and also to load the manhours.The issue here is that there is no set of approved drawings and also no BOQ.I only have drawings in soft form and it is very difficult to study hundreds of drawings on my laptop.Another issue is that the quantities are not calculated.Now I only have a sheet in with overall quantity for each item in each building is calculated.For example the concrete work for complete building is given but not differentiated in foundations,columns,beams and slab concrete.My manager needs me to do some spell and with some megic stick prepare a plan loaded with manhours.
What should I do.From where should I start.I am on vocations and I have to use the above said file only because I am not provided with any other information.
I was wondering if there is some thumb rule to distribute the quantity of an item over different stages.For example if I am given the concrete in Cu.m for whole building then is there any thumb rule to distribute it in foundations,columns,slab etc?
Please Advice.
REgards
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
