Skip to content

project finish date

Sunil BabuMember for 15 years 11 months
Created
3
2
0

Hi friends,

I have finish constraint for my project eg: must finish on or before

12-dec-2012 and I scheduled my project but the project showing the

finish date as 16-feb 2013 why it is happening like this...

your expert advice highly appreciated..

Regards.

Sunil

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Sunil,If you dont want

    Hi Sunil,

    If you dont want your end date to move, used "Mandatory Finish"

    Cheers,

    Daniel

  2. 0
    Sunil Babu ·

    Hi Limson, Thanks for your

    Hi Limson,

    Thanks for your reply

    Regards

    Sunil

  3. 0
    Gary Whitehead ·

    ...but if the date was

    ...but if the date was showing 16th feb with the fniish on or before constraint, this is becuase your schedule is telling you it is impossible to finish by 12th dec.

    Making it a mandatory constraint will make the end date change, but it doesn't mean you will achieve that end date.

     

    Really, you're just hiding the problem, rather than adressing it.

    This is why I do not like mandatory constraints.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?