Skip to content

Creating a project out of the origional project

Sm PumMember for 14 years 11 months
Created
7
5
0

Hello;

 
II am working on a schedule containing around 5000 Activities.Around 3000 Activities Are completed and others are in progress.My manager has asked that create a new schedule containing only the activities that are in progress or not started.Now what trick I should do.i have tried following
 
1-I filtered the activities that are in progress or not started and exported the schedule but of course it will not export only the filtered activities but it exports the complete project.so of no use.
 
2- I opened the two projects togather.Copied activities of one project into other but it is only copying the activities not WBS.
 
3-In WBS Window you can not filter.
 
Please suggest me the solution.
 
Regards

7 replies

Oldest first
  1. 0
    Rafael Davila ·

    I am not a P6 user but would

    I am not a P6 user but would try the following. [depending on how P6 works you shall be able to follow on the idea]

    1. Copy the Existing Job into a Separate Portfolio or WBS.

    2. Identify existing Date Constraints using a user defined field and name them as Old Constraints.

    3. Create within the new Portfolio or WBS a new empty Job/WBS at the same level of the existing..

    4. Move all finished activities to the new Job/WBS.

    5. Export the unfinished activities Job/WBS into an External New Job.

    If this works hopefully you will be able to create the new job without losing any existing and active link to the already finished activities as the process shall transfer the still active links as new date constraints. You shall also be able to discern old date constraints from the newly created date constraints by this procedure.

    Good luck,

    Rafael

  2. 0
    Raymund de Laza ·

    Filter.. Copy.. Paste to

    Filter.. Copy.. Paste to excel...

  3. 0
    Mike Testro ·

    Hi SM Filter all the 100%

    Hi SM

    Filter all the 100% completed tasks and delete them.

    Best regards

    Mike Testro

  4. 0
    Rafael Davila ·

    Merely filtering out finished

    Photobucket

    Merely filtering out finished activities without modeling links still active can lead to a wrong or unfeasible schedule.

    Take a look at the above figure. Say you have finished as planned all activities before your cutoff date set to Sept 17 and you filter out all these as they are finished. You will get a schedule with only two activities but will loose the still active links that prevent them to start on Sept 17.

    Your revised model shall reflect Strip forms A cannot start before Sept 20 and Strip forms B cannot start before Sept 26. This you mimic with the use of date constraints that shall be created by the software on your procedure as manually dealing with hundreds of possible still active links, some SF others SS/FS/FF with some remaining lag as of cutoff.

  5. 0
    Raymund de Laza ·

    Transfer the Completed

    Transfer the Completed Activities to a new Project but maintain the links...

    OPen only the Project that contains the in-progress and not started activities...

    In the schedule option.. uncheck the box "Ignore relationship to and from other projects"

  6. 0
    Rafael Davila ·

    Thanks Raymund.Maybe when you

    Thanks Raymund.

    Maybe when you export using XER files is that the missing links are substituted by date constraints.

    Still I suggest P6 users follow your recommendation and always keep the two separate but linked projects as the created constraints might no longer be valid after subsequent updates.

    I am sure you can add to this posting for the understanding of P6 users.

    For Spider Project users you do not have to move activities, just create another different WBS dictionary that will exclude from display all finished activities and restrict access to other dictionaries, to other users as required. If you send the file to an external user the access restrictions, if any, will be transferred with the file.

    Best regards,

    Rafael

  7. 0
    Rajesh Passi ·

    Hello SM, Step 1. Go to

    Hello SM,

    Step 1. Go to filter option and enable completed activities.

    Step 2. The select all the completed activities which are filtered and delete it.

    Step 3. The go again to filter and disable the completed activities.

    Step 4. You will now see the activities which are in progress or not started.

    Step 5. Now if you import the .xer file your boss will only see the inprogress and not started activities only.

     

    Thank you

    Rajesh

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?