Project tracking - Updating in MPP 2003

Mukesh Kumar KhatriMember for 13 years 11 months
Created
0
2
0

Hi,

I need help for project update,

I have a master schedule of 1350 activities with only task's (no resources and cost) I have saved baseline and inserted column

of Baseline duration and baseline start and finish, and also inserted actual duration and actual start and finish columns and

%age complete for tracking, I m updating actual data like %age complete inserting in activities and start date and finish date as per actual progress. I have also inserted column of start and finish for future progress (to see as planned start and finish) also overall project.

My question is that I have inserted progress in actuals column but in start and finish column (for Future start and finish according ot actual) is same also those activities which dates have been passed and start and finish columns like freezed.

 

thanks and regards,

Mkumar Khatri

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?