Skip to content

MS Project 2007 Adjusting row height when hiding sub tasks

Michael AdesMember for 13 years 10 months
Created
0
4
0

I am using MS project 2007 on a project.

When I hide tasks to produce a summary level schedule I have no control over the row height.

The row height I get seems to be set by the program .

The row height varies between summary tasks.

Any suggestions?

 

Mike

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?