6 Tips to Developing your Project Scope and Schedule – Mind Mapping

Brian JamesMember for 13 years 8 months
Created
1
2
0

I came across this rather different approach to creating your project scope and generating a project schedule. The article describes how mind mapping software helps by firstly brainstorming the project requirements all the way to assigning resources to tasks and exporting to Microsoft Project for detailed schedule development.

http://blog.mindgenius.com/2012/07/6-steps-from-project-scope-to-schedule.html

Considering trying it myself but does anyone have any experience with developing a project scope using mind mapping software or something similar?

1 reply

Oldest first
  1. 0
    Peter Holroyd ·

    Brian,works well, very much

    Brian,

    works well, very much like Interactive Planning Sessions. 

    Drawbacks can be

    Sessions dominated by a senior manager

    Done early on so team not really up to speed with scope or objectives

    Used as a learning session

    Team too timid to contribute

    Political agendas steer the meetings to unsupported decisions

    The mind map has to be interpreted by the planner in MSP - What did the meeting mean by that?

    Give it a go! For schedule I would definitely do a IPA asap in the project lifecycle and repeat it before each stage gate

    Peter