Skip to content

Create S curves with MS PROJECT or PRIMAVERA P6

Jean-Yves MoineMember for 17 years 9 months
Created
0
3
0

 

The S curves, the only way to measure the physical progress of a project.
 
  • Create 26 S curves (baseline early and late, physical progress) in automatic connection with a MS PROJECT or PRIMAVERA P6 schedule.
  • Spread the weights in a linear or Gaussian way over the tasks of schedule.
  • Create S curves with 3 criteria, on the basis of 5 task codes.
  • Manage a schedule up to 10,000 tasks.
 
 
To buy the VBA EXCEL application: http://www.cubixpm-scurves.com/en/

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?