Project resumption after long time of stoppage

Sabry AgourMember for 13 years 4 months
Created
4
3
0

Dear all

Whats the best way to make project resumption after stoppage for a long time ?

is to add stoppage period as nowork in calender or to make suspend and resume or to add new activites 

is there any advice ??

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi SabryAnother way is to set

    Hi Sabry

    Another way is to set a progress data date at the time of restart with the same progress on tasks when stopped or 0% progress for work yet to start.

    The calendar method would also work OK.

    Best regards

    Mike Testro

  2. 0
    Sabry Agour ·

    yes i know but i want show

    yes i know but i want show that in that period work was stoped

  3. 0
    Mike Testro ·

    Hi SabryIn that case use the

    Hi Sabry

    In that case use the calendar.

    Best regards

    Mike Testro

  4. 0
    Sabry Agour ·

    many thanks

    many thanks 