BL PROJECT FINISH DATE IN P6

Tanveer Ahmad NiaziMember for 20 years 10 months
Created
3
2
0

Hi,

We got an EOT approved and submitted the last updated program complying the new project finish date. I submitted the updated schedule as the revised baseline. Now when I maintained the baseline (Save a Copy The Current Project) and assigned accordingly I inserted the columns “BL Project Start” and “BL Project Finish” I am getting a date 93 days later then the data date. Then I updated the schedule at the current dated, and  the finish of project projected to 45 days ahead of current date but the BL Project Finish is still the same (93 days ahead of our cutoff date). I removed the baseline and deleted from the data base but those dated are still there.

How can I show the new project finish date in the BL Project Finish column?

Cheers - Tanveer

3 replies

Oldest first
  1. 0
    Feng Benjamin ·

    Hi,From what I understand of

    Hi,

    From what I understand of your description, it is just a matter of refreshing your schedule using "F5" function.

    Once you do that, the dates should revert to the project finish date you require.

     

    Regards,

    Benjamin

  2. 0
    Gary Whitehead ·

    Also worth checking your

    Also worth checking your admin settings to ensure you are showing baseline and not planned dates -see link below

    http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

  3. 0
    Tanveer Ahmad Niazi ·

    Thank you guys, that helped

    Thank you guys, that helped me alot