BL Project Finish not matching BL Project Early Finish
In the Open Standard
Mark SumnerMember for 13 years 8 months
- Created
- 2
- 3
0
I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates
1. How can I correct this so my BL Project Finish dates match the BL Project Early Finish dates(which are correct)?
2. is there a setting to have the bars reference the BL Project early finish dates and not the useless Project Finish Dates.
If by global change can you please post the setup as I can not seem to create the proper global change to make it work.
Thanks
Mark
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?